The ITAC Statistics page displays the average assessment results for the selected criteria.
9
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $216k | 25k |
MMBtu
|
$8.92 |
- Electrical | $154k | 2,265k |
kWh
|
$0.062 |
- Natural Gas | $10k | 1.5k |
MMBtu
|
$4.81 |
48
Recommendations
5.3
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $47k | 5.7k |
MMBtu
|
23.0% |
- Electrical | $33k | 555k |
kWh
|
24.5% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | $0.1k | |||
Productivity/Other | $1.6k | |||
TOTAL | $49k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
7
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $240k | 28k |
MMBtu
|
$8.85 |
- Electrical | $178k | 2,526k |
kWh
|
$0.064 |
- Natural Gas | $13k | 1.9k |
MMBtu
|
$5.09 |
30
Implemented Recommendations
4.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $27k | 2.9k |
MMBtu
|
10.6% |
- Electrical | $18k | 287k |
kWh
|
11.3% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | $0.1k | |||
Productivity/Other | $1.2k | |||
TOTAL | $29k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |