ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Nonferrous metal die-casting foundries
SIC 2+ Digits Required
3+ Characters Required for Products

54

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,255k 196k
MMBtu
$7.75
- Electrical $566k 11,873k
kWh
$0.060
- Natural Gas $486k 74k
MMBtu
$7.13

468

Recommendations

8.7

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $161k 12k
MMBtu
6.0%
- Electrical $55k 1,148k
kWh
9.7%
- Natural Gas $92k -
MMBtu
-
Waste $103k
Productivity/Other $50k
TOTAL $314k
*May be negative reflecting an increased cost component required to save energy and costs overall

53

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,276k 199k
MMBtu
$7.69
- Electrical $576k 12,079k
kWh
$0.060
- Natural Gas $494k 75k
MMBtu
$7.09

207

Implemented Recommendations

3.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $46k 3.6k
MMBtu
1.8%
- Electrical $18k 349k
kWh
2.9%
- Natural Gas $24k -
MMBtu
-
Waste $0.8k
Productivity/Other $18k
TOTAL $65k
*May be negative reflecting an increased cost component required to save energy and costs overall