The ITAC Statistics page displays the average assessment results for the selected criteria.
NAICS 331512 Steel investment foundries

20

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $733k 498k
MMBtu
$8.12
- Electrical $377k 5,535k
kWh
$0.073
- Natural Gas $222k 441k
MMBtu
$6.04

168

Recommendations

8.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $77k 4.8k
MMBtu
1.0%
- Electrical $31k 472k
kWh
8.5%
- Natural Gas $35k -
MMBtu
-
Waste $1.4k
Productivity/Other $99k
TOTAL $178k
*May be negative reflecting an increased cost component required to save energy and costs overall

19

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $741k 519k
MMBtu
$8.23
- Electrical $387k 5,524k
kWh
$0.076
- Natural Gas $226k 462k
MMBtu
$6.14

81

Implemented Recommendations

4.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $24k 2.1k
MMBtu
0.4%
- Electrical $15k 202k
kWh
3.7%
- Natural Gas $6.6k -
MMBtu
-
Waste $1.0k
Productivity/Other $4.3k
TOTAL $30k
*May be negative reflecting an increased cost component required to save energy and costs overall