The ITAC Statistics page displays the average assessment results for the selected criteria.
27
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $692k | 117k |
MMBtu
|
$9.02 |
- Electrical | $434k | 6,928k |
kWh
|
$0.080 |
- Natural Gas | $160k | 44k |
MMBtu
|
$7.18 |
198
Recommendations
7.3
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $46k | 2.7k |
MMBtu
|
2.3% |
- Electrical | $24k | 268k |
kWh
|
3.9% |
- Natural Gas | $14k | - |
MMBtu
|
- |
Waste | $62k | |||
Productivity/Other | $26k | |||
TOTAL | $134k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
26
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $709k | 121k |
MMBtu
|
$8.92 |
- Electrical | $445k | 7,122k |
kWh
|
$0.080 |
- Natural Gas | $166k | 46k |
MMBtu
|
$7.23 |
80
Implemented Recommendations
3.1
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $23k | 2.0k |
MMBtu
|
1.7% |
- Electrical | $13k | 196k |
kWh
|
2.7% |
- Natural Gas | $6.9k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $1.8k | |||
TOTAL | $25k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |