ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Rolling and drawing of purchased steel
SIC 2+ Digits Required
3+ Characters Required for Products

70

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,386k 286k
MMBtu
$7.75
- Electrical $743k 16,896k
kWh
$0.058
- Natural Gas $393k 111k
MMBtu
$12.11

684

Recommendations

9.8

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $163k 16k
MMBtu
5.6%
- Electrical $73k 1,560k
kWh
9.2%
- Natural Gas $42k -
MMBtu
-
Waste $13k
Productivity/Other $49k
TOTAL $225k
*May be negative reflecting an increased cost component required to save energy and costs overall

65

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,406k 286k
MMBtu
$7.42
- Electrical $751k 17,211k
kWh
$0.056
- Natural Gas $395k 108k
MMBtu
$6.61

268

Implemented Recommendations

4.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $47k 3.7k
MMBtu
1.3%
- Electrical $17k 356k
kWh
2.1%
- Natural Gas $17k -
MMBtu
-
Waste $3.3k
Productivity/Other $17k
TOTAL $68k