ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Mineral wool manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

15

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,217k 332k
MMBtu
$7.40
- Electrical $609k 16,603k
kWh
$0.049
- Natural Gas $876k 146k
MMBtu
$6.78

133

Recommendations

8.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $255k 14k
MMBtu
4.3%
- Electrical $67k 1,398k
kWh
8.4%
- Natural Gas $139k -
MMBtu
-
Waste $38k
Productivity/Other $5.6k
TOTAL $299k
*May be negative reflecting an increased cost component required to save energy and costs overall

12

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,626k 398k
MMBtu
$6.96
- Electrical $675k 19,561k
kWh
$0.040
- Natural Gas $1,063k 177k
MMBtu
$6.17

58

Implemented Recommendations

4.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $139k 5.6k
MMBtu
1.4%
- Electrical $21k 550k
kWh
2.8%
- Natural Gas $83k -
MMBtu
-
Waste $0.1k
Productivity/Other ($-0.5)k
TOTAL $139k
*May be negative reflecting an increased cost component required to save energy and costs overall