The ITAC Statistics page displays the average assessment results for the selected criteria.
28
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $4,039k | 756k |
MMBtu
|
$8.68 |
- Electrical | $905k | 15,576k |
kWh
|
$0.072 |
- Natural Gas | $2,698k | 504k |
MMBtu
|
$7.43 |
178
Recommendations
6.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $463k | 49k |
MMBtu
|
6.5% |
- Electrical | $266k | 4,790k |
kWh
|
30.8% |
- Natural Gas | $103k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $388k | |||
TOTAL | $851k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
28
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $4,039k | 756k |
MMBtu
|
$8.68 |
- Electrical | $905k | 15,576k |
kWh
|
$0.072 |
- Natural Gas | $2,698k | 504k |
MMBtu
|
$7.43 |
76
Implemented Recommendations
2.7
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $61k | 15k |
MMBtu
|
2.0% |
- Electrical | $77k | 1,480k |
kWh
|
9.5% |
- Natural Gas | ($-50.1)k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $31k | |||
TOTAL | $91k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |