ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other concrete product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

31

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $576k 77k
MMBtu
$9.65
- Electrical $236k 4,580k
kWh
$0.069
- Natural Gas $190k 26k
MMBtu
$6.67

222

Recommendations

7.2

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $68k 5.3k
MMBtu
6.8%
- Electrical $32k 513k
kWh
11.2%
- Natural Gas $14k -
MMBtu
-
Waste $0.1k
Productivity/Other $14k
TOTAL $82k
*May be negative reflecting an increased cost component required to save energy and costs overall

28

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $608k 82k
MMBtu
$9.45
- Electrical $252k 4,934k
kWh
$0.068
- Natural Gas $204k 27k
MMBtu
$7.08

86

Implemented Recommendations

3.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $29k 1.6k
MMBtu
2.0%
- Electrical $10k 157k
kWh
3.2%
- Natural Gas $11k -
MMBtu
-
Waste $0.0k
Productivity/Other $3.1k
TOTAL $32k
*May be negative reflecting an increased cost component required to save energy and costs overall