ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Concrete block and brick manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

14

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $651k 84k
MMBtu
$11.90
- Electrical $213k 2,525k
kWh
$0.077
- Natural Gas $287k 57k
MMBtu
$6.26

93

Recommendations

6.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $55k 2.7k
MMBtu
3.2%
- Electrical $14k 260k
kWh
10.3%
- Natural Gas $18k -
MMBtu
-
Waste $2.5k
Productivity/Other $37k
TOTAL $94k
*May be negative reflecting an increased cost component required to save energy and costs overall

13

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $608k 64k
MMBtu
$12.55
- Electrical $217k 2,468k
kWh
$0.079
- Natural Gas $245k 38k
MMBtu
$6.53

36

Implemented Recommendations

2.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $15k 1.4k
MMBtu
2.2%
- Electrical $10.0k 140k
kWh
5.7%
- Natural Gas $2.6k -
MMBtu
-
Waste -
Productivity/Other $0.1k
TOTAL $15k
*May be negative reflecting an increased cost component required to save energy and costs overall