The ITAC Statistics page displays the average assessment results for the selected criteria.
362
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,962k | 369k |
MMBtu
|
$9.20 |
- Electrical | $775k | 15,357k |
kWh
|
$0.068 |
- Natural Gas | $820k | 160k |
MMBtu
|
$5.80 |
2,675
Recommendations
7.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $202k | 21k |
MMBtu
|
5.7% |
- Electrical | $108k | 2,064k |
kWh
|
13.4% |
- Natural Gas | $50k | - |
MMBtu
|
- |
Waste | $4.2k | |||
Productivity/Other | $75k | |||
TOTAL | $281k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
350
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,991k | 377k |
MMBtu
|
$9.11 |
- Electrical | $784k | 15,644k |
kWh
|
$0.068 |
- Natural Gas | $836k | 163k |
MMBtu
|
$5.66 |
1,191
Implemented Recommendations
3.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $49k | 5.3k |
MMBtu
|
1.4% |
- Electrical | $30k | 516k |
kWh
|
3.3% |
- Natural Gas | $5.8k | - |
MMBtu
|
- |
Waste | $1.0k | |||
Productivity/Other | $15k | |||
TOTAL | $64k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |