ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other rubber product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

116

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $819k 112k
MMBtu
$9.04
- Electrical $498k 8,063k
kWh
$0.073
- Natural Gas $145k 29k
MMBtu
$7.41

1,027

Recommendations

8.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $126k 12k
MMBtu
10.5%
- Electrical $90k 1,148k
kWh
14.2%
- Natural Gas $16k -
MMBtu
-
Waste $9.3k
Productivity/Other $35k
TOTAL $170k
*May be negative reflecting an increased cost component required to save energy and costs overall

108

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $826k 115k
MMBtu
$8.86
- Electrical $500k 8,281k
kWh
$0.072
- Natural Gas $149k 30k
MMBtu
$7.39

464

Implemented Recommendations

4.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $54k 4.9k
MMBtu
4.3%
- Electrical $35k 476k
kWh
5.8%
- Natural Gas $10k -
MMBtu
-
Waste $4.6k
Productivity/Other $21k
TOTAL $80k
*May be negative reflecting an increased cost component required to save energy and costs overall