ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC Fuel switching
NAICS Plastics plumbing fixture manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

18

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $528k 63k
MMBtu
$9.38
- Electrical $208k 3,951k
kWh
$0.061
- Natural Gas $159k 20k
MMBtu
$7.58

124

Recommendations

6.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $59k 3.1k
MMBtu
4.8%
- Electrical $19k 299k
kWh
7.6%
- Natural Gas $32k -
MMBtu
-
Waste $4.9k
Productivity/Other $53k
TOTAL $117k
*May be negative reflecting an increased cost component required to save energy and costs overall

17

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $469k 63k
MMBtu
$8.68
- Electrical $213k 4,069k
kWh
$0.060
- Natural Gas $169k 21k
MMBtu
$8.03

52

Implemented Recommendations

3.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $17k 1.0k
MMBtu
1.5%
- Electrical $5.7k 93k
kWh
2.3%
- Natural Gas $8.9k -
MMBtu
-
Waste -
Productivity/Other $36k
TOTAL $53k