ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Custom compounding of purchased resins
SIC 2+ Digits Required
3+ Characters Required for Products

22

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $955k 129k
MMBtu
$8.13
- Electrical $651k 11,847k
kWh
$0.061
- Natural Gas $55k 7.0k
MMBtu
$6.16

190

Recommendations

8.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $73k 7.9k
MMBtu
6.1%
- Electrical $40k 771k
kWh
6.5%
- Natural Gas $14k -
MMBtu
-
Waste $6.1k
Productivity/Other $47k
TOTAL $126k
*May be negative reflecting an increased cost component required to save energy and costs overall

21

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $860k 122k
MMBtu
$7.98
- Electrical $615k 11,447k
kWh
$0.060
- Natural Gas $42k 4.6k
MMBtu
$6.18

80

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $29k 3.2k
MMBtu
2.6%
- Electrical $13k 312k
kWh
2.7%
- Natural Gas $7.2k -
MMBtu
-
Waste $0.6k
Productivity/Other $19k
TOTAL $48k
*May be negative reflecting an increased cost component required to save energy and costs overall