The ITAC Statistics page displays the average assessment results for the selected criteria.
110
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $1,649k | 270k |
MMBtu
|
$8.95 |
| - Electrical | $689k | 13,240k |
kWh
|
$0.067 |
| - Natural Gas | $658k | 122k |
MMBtu
|
$6.25 |
917
Recommendations
8.3
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $210k | 20k |
MMBtu
|
7.3% |
| - Electrical | $120k | 1,913k |
kWh
|
14.4% |
| - Natural Gas | $39k | - |
MMBtu
|
- |
| Waste | $11k | |||
| Productivity/Other | $17k | |||
| TOTAL | $238k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
104
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $1,687k | 279k |
MMBtu
|
$8.96 |
| - Electrical | $701k | 13,632k |
kWh
|
$0.067 |
| - Natural Gas | $683k | 127k |
MMBtu
|
$6.23 |
406
Implemented Recommendations
3.9
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $102k | 4.2k |
MMBtu
|
1.5% |
| - Electrical | $25k | 413k |
kWh
|
3.0% |
| - Natural Gas | $51k | - |
MMBtu
|
- |
| Waste | $1.0k | |||
| Productivity/Other | $8.9k | |||
| TOTAL | $112k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||