ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Paint, coating, and adhesive manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

86

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $564k 94k
MMBtu
$9.51
- Electrical $277k 5,295k
kWh
$0.071
- Natural Gas $169k 40k
MMBtu
$6.74

727

Recommendations

8.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $80k 5.3k
MMBtu
5.6%
- Electrical $36k 515k
kWh
9.7%
- Natural Gas $27k -
MMBtu
-
Waste $8.6k
Productivity/Other $5.0k
TOTAL $94k
*May be negative reflecting an increased cost component required to save energy and costs overall

79

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $519k 89k
MMBtu
$9.34
- Electrical $254k 4,967k
kWh
$0.071
- Natural Gas $166k 38k
MMBtu
$6.80

310

Implemented Recommendations

3.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $31k 2.1k
MMBtu
2.4%
- Electrical $18k 208k
kWh
4.2%
- Natural Gas $9.6k -
MMBtu
-
Waste $3.0k
Productivity/Other $3.0k
TOTAL $37k
*May be negative reflecting an increased cost component required to save energy and costs overall