The ITAC Statistics page displays the average assessment results for the selected criteria.
55
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $2,731k | 506k |
MMBtu
|
$7.10 |
- Electrical | $835k | 15,812k |
kWh
|
$0.059 |
- Natural Gas | $1,527k | 315k |
MMBtu
|
$5.70 |
447
Recommendations
8.1
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $345k | 34k |
MMBtu
|
6.7% |
- Electrical | $181k | 3,293k |
kWh
|
20.8% |
- Natural Gas | $88k | - |
MMBtu
|
- |
Waste | $4.4k | |||
Productivity/Other | $91k | |||
TOTAL | $441k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
50
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $2,964k | 550k |
MMBtu
|
$6.92 |
- Electrical | $902k | 17,161k |
kWh
|
$0.057 |
- Natural Gas | $1,664k | 343k |
MMBtu
|
$5.91 |
176
Implemented Recommendations
3.5
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $84k | 4.6k |
MMBtu
|
0.8% |
- Electrical | $25k | 449k |
kWh
|
2.6% |
- Natural Gas | $54k | - |
MMBtu
|
- |
Waste | $3.5k | |||
Productivity/Other | $63k | |||
TOTAL | $150k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |