The ITAC Statistics page displays the average assessment results for the selected criteria.
10
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $6,966k | 1,522k |
MMBtu
|
$6.60 |
- Electrical | $4,889k | 122,389k |
kWh
|
$0.057 |
- Natural Gas | $1,963k | 265k |
MMBtu
|
$4.22 |
67
Recommendations
6.7
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $198k | 12k |
MMBtu
|
0.8% |
- Electrical | $63k | 1,154k |
kWh
|
0.9% |
- Natural Gas | $124k | - |
MMBtu
|
- |
Waste | $3.2k | |||
Productivity/Other | $13k | |||
TOTAL | $215k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
10
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $6,966k | 1,522k |
MMBtu
|
$6.60 |
- Electrical | $4,889k | 122,389k |
kWh
|
$0.057 |
- Natural Gas | $1,963k | 265k |
MMBtu
|
$4.22 |
26
Implemented Recommendations
2.6
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $148k | 5.8k |
MMBtu
|
0.4% |
- Electrical | $31k | 565k |
kWh
|
0.5% |
- Natural Gas | $112k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $13k | |||
TOTAL | $161k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |