The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC | 2+ Digits Required | |
NAICS | Petrochemical manufacturing | |
SIC | 2+ Digits Required | |
3+ Characters Required for Products |
11
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $11,205k | 3,299k |
MMBtu
|
$6.46 |
- Electrical | $3,668k | 127,696k |
kWh
|
$0.061 |
- Natural Gas | $6,108k | 1,981k |
MMBtu
|
$5.00 |
82
Recommendations
7.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $3,440k | 28k |
MMBtu
|
0.9% |
- Electrical | $152k | 2,772k |
kWh
|
2.2% |
- Natural Gas | $3,274k | - |
MMBtu
|
- |
Waste | $209k | |||
Productivity/Other | ($-1.0)k | |||
TOTAL | $3,648k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
11
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $11,205k | 3,299k |
MMBtu
|
$6.46 |
- Electrical | $3,668k | 127,696k |
kWh
|
$0.061 |
- Natural Gas | $6,108k | 1,981k |
MMBtu
|
$5.00 |
26
Implemented Recommendations
2.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $103k | 14k |
MMBtu
|
0.4% |
- Electrical | $65k | 1,318k |
kWh
|
1.0% |
- Natural Gas | $35k | - |
MMBtu
|
- |
Waste | $13k | |||
Productivity/Other | $1.6k | |||
TOTAL | $117k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |