ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Chemical manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

742

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,895k 434k
MMBtu
$8.51
- Electrical $842k 18,012k
kWh
$0.075
- Natural Gas $716k 232k
MMBtu
$6.60

5,878

Recommendations

7.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $238k 19k
MMBtu
4.5%
- Electrical $109k 1,901k
kWh
10.6%
- Natural Gas $94k -
MMBtu
-
Waste $14k
Productivity/Other $35k
TOTAL $287k
*May be negative reflecting an increased cost component required to save energy and costs overall

684

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,965k 457k
MMBtu
$8.31
- Electrical $872k 18,748k
kWh
$0.075
- Natural Gas $751k 245k
MMBtu
$6.62

2,428

Implemented Recommendations

3.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $79k 5.9k
MMBtu
1.3%
- Electrical $36k 575k
kWh
3.1%
- Natural Gas $35k -
MMBtu
-
Waste $3.9k
Productivity/Other $21k
TOTAL $104k
*May be negative reflecting an increased cost component required to save energy and costs overall