The ITAC Statistics page displays the average assessment results for the selected criteria.
31
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $7,613k | 1,052k |
MMBtu
|
$8.16 |
- Electrical | $3,275k | 47,568k |
kWh
|
$0.068 |
- Natural Gas | $4,070k | 526k |
MMBtu
|
$6.46 |
234
Recommendations
7.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $415k | 8.0k |
MMBtu
|
0.8% |
- Electrical | $46k | 780k |
kWh
|
1.6% |
- Natural Gas | $320k | - |
MMBtu
|
- |
Waste | $2.2k | |||
Productivity/Other | $35k | |||
TOTAL | $451k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
29
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $8,031k | 1,104k |
MMBtu
|
$8.35 |
- Electrical | $3,453k | 50,148k |
kWh
|
$0.068 |
- Natural Gas | $4,315k | 549k |
MMBtu
|
$6.70 |
95
Implemented Recommendations
3.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $139k | 3.1k |
MMBtu
|
0.3% |
- Electrical | $18k | 303k |
kWh
|
0.6% |
- Natural Gas | $100k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $6.9k | |||
TOTAL | $146k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |