ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Asphalt paving, roofing, and saturated materials manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

80

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $998k 195k
MMBtu
$7.72
- Electrical $283k 4,317k
kWh
$0.080
- Natural Gas $507k 135k
MMBtu
$5.12

565

Recommendations

7.1

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $146k 5.5k
MMBtu
2.8%
- Electrical $37k 534k
kWh
12.4%
- Natural Gas $55k -
MMBtu
-
Waste $8.1k
Productivity/Other $67k
TOTAL $222k
*May be negative reflecting an increased cost component required to save energy and costs overall

76

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,023k 201k
MMBtu
$7.75
- Electrical $291k 4,490k
kWh
$0.076
- Natural Gas $516k 138k
MMBtu
$5.12

266

Implemented Recommendations

3.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $61k 2.1k
MMBtu
1.0%
- Electrical $16k 202k
kWh
4.5%
- Natural Gas $17k -
MMBtu
-
Waste $0.2k
Productivity/Other $46k
TOTAL $108k
*May be negative reflecting an increased cost component required to save energy and costs overall