The ITAC Statistics page displays the average assessment results for the selected criteria.
242
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $671k | 89k |
MMBtu
|
$9.28 |
- Electrical | $386k | 6,782k |
kWh
|
$0.16 |
- Natural Gas | $132k | 19k |
MMBtu
|
$6.80 |
1,951
Recommendations
8.1
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $76k | 7.3k |
MMBtu
|
8.2% |
- Electrical | $43k | 711k |
kWh
|
10.5% |
- Natural Gas | $18k | - |
MMBtu
|
- |
Waste | $2.0k | |||
Productivity/Other | $37k | |||
TOTAL | $114k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
233
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $686k | 91k |
MMBtu
|
$9.27 |
- Electrical | $396k | 6,955k |
kWh
|
$0.17 |
- Natural Gas | $136k | 19k |
MMBtu
|
$6.79 |
897
Implemented Recommendations
3.8
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $38k | 3.6k |
MMBtu
|
3.9% |
- Electrical | $22k | 348k |
kWh
|
5.0% |
- Natural Gas | $10k | - |
MMBtu
|
- |
Waste | $0.3k | |||
Productivity/Other | $10k | |||
TOTAL | $49k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |