The ITAC Statistics page displays the average assessment results for the selected criteria.
63
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $751k | 100k |
MMBtu
|
$8.03 |
- Electrical | $397k | 7,071k |
kWh
|
$0.062 |
- Natural Gas | $204k | 28k |
MMBtu
|
$6.80 |
481
Recommendations
7.6
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $103k | 8.8k |
MMBtu
|
8.7% |
- Electrical | $47k | 854k |
kWh
|
12.1% |
- Natural Gas | $40k | - |
MMBtu
|
- |
Waste | $1.9k | |||
Productivity/Other | $31k | |||
TOTAL | $135k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
58
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $650k | 84k |
MMBtu
|
$8.10 |
- Electrical | $322k | 5,616k |
kWh
|
$0.062 |
- Natural Gas | $198k | 26k |
MMBtu
|
$6.86 |
185
Implemented Recommendations
3.2
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $29k | 3.3k |
MMBtu
|
3.9% |
- Electrical | $17k | 324k |
kWh
|
5.8% |
- Natural Gas | $7.7k | - |
MMBtu
|
- |
Waste | $0.7k | |||
Productivity/Other | $7.6k | |||
TOTAL | $38k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |