ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Paper manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

384

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,205k 509k
MMBtu
$8.21
- Electrical $1,010k 22,138k
kWh
$0.065
- Natural Gas $738k 224k
MMBtu
$6.59

3,077

Recommendations

8.0

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $183k 18k
MMBtu
3.5%
- Electrical $77k 1,753k
kWh
7.9%
- Natural Gas $50k -
MMBtu
-
Waste $7.4k
Productivity/Other $95k
TOTAL $285k
*May be negative reflecting an increased cost component required to save energy and costs overall

368

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,260k 525k
MMBtu
$8.13
- Electrical $1,029k 22,671k
kWh
$0.065
- Natural Gas $763k 232k
MMBtu
$6.57

1,306

Implemented Recommendations

3.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $71k 3.7k
MMBtu
0.7%
- Electrical $20k 364k
kWh
1.6%
- Natural Gas $24k -
MMBtu
-
Waste $0.8k
Productivity/Other $11k
TOTAL $82k
*May be negative reflecting an increased cost component required to save energy and costs overall