ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other wood product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

222

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $734k 135k
MMBtu
$9.21
- Electrical $407k 7,548k
kWh
$0.074
- Natural Gas $128k 21k
MMBtu
$5.11

1,591

Recommendations

7.2

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $90k 10k
MMBtu
7.6%
- Electrical $57k 996k
kWh
13.2%
- Natural Gas $9.6k -
MMBtu
-
Waste $1.8k
Productivity/Other $55k
TOTAL $146k
*May be negative reflecting an increased cost component required to save energy and costs overall

212

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $734k 138k
MMBtu
$9.11
- Electrical $398k 7,596k
kWh
$0.073
- Natural Gas $130k 21k
MMBtu
$5.05

719

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $45k 4.8k
MMBtu
3.5%
- Electrical $29k 467k
kWh
6.1%
- Natural Gas $5.7k -
MMBtu
-
Waste $0.3k
Productivity/Other $13k
TOTAL $59k
*May be negative reflecting an increased cost component required to save energy and costs overall