ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other wood product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

240

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $724k 129k
MMBtu
$9.83
- Electrical $395k 7,189k
kWh
$0.077
- Natural Gas $131k 21k
MMBtu
$5.22

1,711

Recommendations

7.1

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $93k 9.7k
MMBtu
7.5%
- Electrical $56k 948k
kWh
13.2%
- Natural Gas $11k -
MMBtu
-
Waste $1.8k
Productivity/Other $62k
TOTAL $157k
*May be negative reflecting an increased cost component required to save energy and costs overall

219

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $733k 135k
MMBtu
$9.24
- Electrical $405k 7,559k
kWh
$0.074
- Natural Gas $126k 21k
MMBtu
$5.01

738

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $44k 4.7k
MMBtu
3.4%
- Electrical $28k 454k
kWh
6.0%
- Natural Gas $5.5k -
MMBtu
-
Waste $0.3k
Productivity/Other $14k
TOTAL $58k
*May be negative reflecting an increased cost component required to save energy and costs overall