ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other wood product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

231

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $720k 131k
MMBtu
$9.46
- Electrical $398k 7,323k
kWh
$0.075
- Natural Gas $125k 20k
MMBtu
$5.12

1,651

Recommendations

7.1

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $93k 10.0k
MMBtu
7.6%
- Electrical $57k 972k
kWh
13.3%
- Natural Gas $9.6k -
MMBtu
-
Waste $1.8k
Productivity/Other $57k
TOTAL $152k
*May be negative reflecting an increased cost component required to save energy and costs overall

218

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $735k 136k
MMBtu
$9.21
- Electrical $406k 7,586k
kWh
$0.074
- Natural Gas $126k 21k
MMBtu
$5.04

731

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $44k 4.7k
MMBtu
3.4%
- Electrical $28k 455k
kWh
6.0%
- Natural Gas $5.5k -
MMBtu
-
Waste $0.3k
Productivity/Other $13k
TOTAL $57k
*May be negative reflecting an increased cost component required to save energy and costs overall