ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Footwear manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

4

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $265k 25k
MMBtu
$11.31
- Electrical $131k 1,948k
kWh
$0.065
- Natural Gas $20k 3.6k
MMBtu
$2.79

26

Recommendations

6.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $22k 1.9k
MMBtu
7.6%
- Electrical $12k 185k
kWh
9.5%
- Natural Gas $3.2k -
MMBtu
-
Waste $9.2k
Productivity/Other $1.0k
TOTAL $32k
*May be negative reflecting an increased cost component required to save energy and costs overall

2

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $356k 35k
MMBtu
$10.61
- Electrical $178k 2,690k
kWh
$0.066
- Natural Gas $39k 7.2k
MMBtu
$5.58

9

Implemented Recommendations

4.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $12k 0.6k
MMBtu
1.7%
- Electrical $3.8k 58k
kWh
2.1%
- Natural Gas $6.0k -
MMBtu
-
Waste -
Productivity/Other $0.1k
TOTAL $12k
*May be negative reflecting an increased cost component required to save energy and costs overall