38
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $611k | 221k |
MMBtu
|
$8.89 |
- Electrical | $392k | 7,365k |
kWh
|
$0.072 |
- Natural Gas | $118k | 145k |
MMBtu
|
$7.29 |
260
Recommendations
6.8
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $64k | 6.1k |
MMBtu
|
2.8% |
- Electrical | $39k | 598k |
kWh
|
8.1% |
- Natural Gas | $12k | - |
MMBtu
|
- |
Waste | $0.5k | |||
Productivity/Other | $10k | |||
TOTAL | $75k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
36
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $631k | 232k |
MMBtu
|
$8.48 |
- Electrical | $411k | 7,706k |
kWh
|
$0.074 |
- Natural Gas | $122k | 153k |
MMBtu
|
$6.74 |
120
Implemented Recommendations
3.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $20k | 2.6k |
MMBtu
|
1.1% |
- Electrical | $18k | 250k |
kWh
|
3.2% |
- Natural Gas | $0.6k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $0.7k | |||
TOTAL | $21k | |||