ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Fabric mills
SIC 2+ Digits Required
3+ Characters Required for Products

51

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,359k 235k
MMBtu
$8.21
- Electrical $745k 15,129k
kWh
$0.062
- Natural Gas $315k 52k
MMBtu
$5.81

395

Recommendations

7.7

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $153k 11k
MMBtu
4.8%
- Electrical $64k 1,098k
kWh
7.3%
- Natural Gas $35k -
MMBtu
-
Waste $1.8k
Productivity/Other $14k
TOTAL $169k
*May be negative reflecting an increased cost component required to save energy and costs overall

47

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,400k 245k
MMBtu
$7.82
- Electrical $767k 15,728k
kWh
$0.059
- Natural Gas $334k 55k
MMBtu
$5.97

179

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $62k 3.9k
MMBtu
1.6%
- Electrical $22k 385k
kWh
2.4%
- Natural Gas $19k -
MMBtu
-
Waste $0.1k
Productivity/Other $6.0k
TOTAL $68k
*May be negative reflecting an increased cost component required to save energy and costs overall