ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Fiber, yarn, and thread mills
SIC 2+ Digits Required
3+ Characters Required for Products

27

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,861k 340k
MMBtu
$5.87
- Electrical $1,328k 30,732k
kWh
$0.047
- Natural Gas $163k 23k
MMBtu
$3.02

209

Recommendations

7.7

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $140k 20k
MMBtu
6.0%
- Electrical $86k 1,979k
kWh
6.4%
- Natural Gas $33k -
MMBtu
-
Waste $0.6k
Productivity/Other $5.3k
TOTAL $146k
*May be negative reflecting an increased cost component required to save energy and costs overall

27

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,861k 340k
MMBtu
$5.87
- Electrical $1,328k 30,732k
kWh
$0.047
- Natural Gas $163k 23k
MMBtu
$3.02

106

Implemented Recommendations

3.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $59k 9.3k
MMBtu
2.7%
- Electrical $40k 905k
kWh
2.9%
- Natural Gas $12k -
MMBtu
-
Waste -
Productivity/Other $0.4k
TOTAL $60k
*May be negative reflecting an increased cost component required to save energy and costs overall