The ITAC Statistics page displays the average assessment results for the selected criteria.
281
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $960k | 127k |
MMBtu
|
$10.86 |
- Electrical | $500k | 7,633k |
kWh
|
$0.23 |
- Natural Gas | $228k | 42k |
MMBtu
|
$6.61 |
2,111
Recommendations
7.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $130k | 11k |
MMBtu
|
8.8% |
- Electrical | $82k | 1,090k |
kWh
|
14.3% |
- Natural Gas | $22k | - |
MMBtu
|
- |
Waste | $15k | |||
Productivity/Other | $62k | |||
TOTAL | $208k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
255
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $876k | 117k |
MMBtu
|
$10.52 |
- Electrical | $464k | 7,161k |
kWh
|
$0.25 |
- Natural Gas | $223k | 39k |
MMBtu
|
$6.50 |
911
Implemented Recommendations
3.6
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $41k | 3.4k |
MMBtu
|
2.9% |
- Electrical | $26k | 327k |
kWh
|
4.6% |
- Natural Gas | $9.0k | - |
MMBtu
|
- |
Waste | $6.9k | |||
Productivity/Other | $28k | |||
TOTAL | $76k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |