The ITAC Statistics page displays the average assessment results for the selected criteria.
1
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $537k | 85k |
MMBtu
|
$6.35 |
- Electrical | $284k | 6,569k |
kWh
|
$0.043 |
- Natural Gas | $38k | 17k |
MMBtu
|
$2.18 |
4
Recommendations
4.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $49k | 4.5k |
MMBtu
|
5.4% |
- Electrical | $19k | 442k |
kWh
|
6.7% |
- Natural Gas | $2.1k | - |
MMBtu
|
- |
Waste | $0.0k | |||
Productivity/Other | - | |||
TOTAL | $49k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
1
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $537k | 85k |
MMBtu
|
$6.35 |
- Electrical | $284k | 6,569k |
kWh
|
$0.043 |
- Natural Gas | $38k | 17k |
MMBtu
|
$2.18 |
4
Implemented Recommendations
4.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $49k | 4.5k |
MMBtu
|
5.4% |
- Electrical | $19k | 442k |
kWh
|
6.7% |
- Natural Gas | $2.1k | - |
MMBtu
|
- |
Waste | $0.0k | |||
Productivity/Other | - | |||
TOTAL | $49k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |