ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS All other food manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

101

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,073k 149k
MMBtu
$9.24
- Electrical $581k 9,221k
kWh
$0.072
- Natural Gas $258k 51k
MMBtu
$5.56

750

Recommendations

7.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $123k 11k
MMBtu
7.6%
- Electrical $78k 1,108k
kWh
12.0%
- Natural Gas $15k -
MMBtu
-
Waste $5.4k
Productivity/Other $77k
TOTAL $206k
*May be negative reflecting an increased cost component required to save energy and costs overall

91

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,028k 146k
MMBtu
$9.05
- Electrical $553k 8,985k
kWh
$0.071
- Natural Gas $265k 51k
MMBtu
$5.55

292

Implemented Recommendations

3.2

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $50k 5.4k
MMBtu
3.7%
- Electrical $33k 524k
kWh
5.8%
- Natural Gas $8.7k -
MMBtu
-
Waste $0.7k
Productivity/Other $20k
TOTAL $71k
*May be negative reflecting an increased cost component required to save energy and costs overall