21
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $805k | 111k |
MMBtu
|
$9.37 |
- Electrical | $491k | 7,076k |
kWh
|
$0.091 |
- Natural Gas | $241k | 38k |
MMBtu
|
$6.26 |
140
Recommendations
6.7
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $71k | 6.3k |
MMBtu
|
5.7% |
- Electrical | $48k | 617k |
kWh
|
8.7% |
- Natural Gas | $18k | - |
MMBtu
|
- |
Waste | $0.5k | |||
Productivity/Other | $20k | |||
TOTAL | $92k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
18
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $889k | 125k |
MMBtu
|
$8.55 |
- Electrical | $544k | 7,955k |
kWh
|
$0.084 |
- Natural Gas | $267k | 43k |
MMBtu
|
$6.33 |
50
Implemented Recommendations
2.8
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $17k | 1.7k |
MMBtu
|
1.4% |
- Electrical | $11k | 167k |
kWh
|
2.1% |
- Natural Gas | $4.1k | - |
MMBtu
|
- |
Waste | $0.3k | |||
Productivity/Other | $10k | |||
TOTAL | $28k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |