ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other snack food manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

35

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,340k 218k
MMBtu
$7.18
- Electrical $457k 7,982k
kWh
$0.064
- Natural Gas $678k 132k
MMBtu
$5.66

254

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $94k 6.4k
MMBtu
2.9%
- Electrical $54k 626k
kWh
7.8%
- Natural Gas $35k -
MMBtu
-
Waste $18k
Productivity/Other $26k
TOTAL $138k
*May be negative reflecting an increased cost component required to save energy and costs overall

33

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,410k 229k
MMBtu
$7.10
- Electrical $480k 8,406k
kWh
$0.064
- Natural Gas $713k 139k
MMBtu
$5.54

111

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $38k 3.5k
MMBtu
1.5%
- Electrical $27k 339k
kWh
4.0%
- Natural Gas $7.2k -
MMBtu
-
Waste $10k
Productivity/Other $8.2k
TOTAL $56k
*May be negative reflecting an increased cost component required to save energy and costs overall