ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Snack food manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

60

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,159k 174k
MMBtu
$8.35
- Electrical $491k 7,740k
kWh
$0.070
- Natural Gas $491k 89k
MMBtu
$5.52

462

Recommendations

7.7

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $120k 10k
MMBtu
5.8%
- Electrical $81k 990k
kWh
12.8%
- Natural Gas $26k -
MMBtu
-
Waste $12k
Productivity/Other $17k
TOTAL $149k
*May be negative reflecting an increased cost component required to save energy and costs overall

56

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,228k 184k
MMBtu
$8.23
- Electrical $521k 8,221k
kWh
$0.069
- Natural Gas $521k 95k
MMBtu
$5.34

214

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $50k 4.4k
MMBtu
2.4%
- Electrical $38k 430k
kWh
5.2%
- Natural Gas $7.4k -
MMBtu
-
Waste $6.4k
Productivity/Other $5.2k
TOTAL $61k
*May be negative reflecting an increased cost component required to save energy and costs overall