ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Animal (except poultry) slaughtering
SIC 2+ Digits Required
3+ Characters Required for Products

42

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,515k 203k
MMBtu
$8.51
- Electrical $640k 12,862k
kWh
$0.065
- Natural Gas $491k 71k
MMBtu
$6.49

352

Recommendations

8.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $128k 14k
MMBtu
6.7%
- Electrical $73k 1,327k
kWh
10.3%
- Natural Gas $36k -
MMBtu
-
Waste $7.1k
Productivity/Other $18k
TOTAL $152k
*May be negative reflecting an increased cost component required to save energy and costs overall

39

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,607k 216k
MMBtu
$8.11
- Electrical $678k 13,691k
kWh
$0.060
- Natural Gas $521k 75k
MMBtu
$6.74

141

Implemented Recommendations

3.6

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $39k 3.4k
MMBtu
1.6%
- Electrical $19k 331k
kWh
2.4%
- Natural Gas $16k -
MMBtu
-
Waste $3.0k
Productivity/Other $3.8k
TOTAL $46k
*May be negative reflecting an increased cost component required to save energy and costs overall