The ITAC Statistics page displays the average assessment results for the selected criteria.
179
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,658k | 271k |
MMBtu
|
$7.92 |
- Electrical | $759k | 15,821k |
kWh
|
$0.064 |
- Natural Gas | $579k | 106k |
MMBtu
|
$6.41 |
1,462
Recommendations
8.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $155k | 11k |
MMBtu
|
4.2% |
- Electrical | $71k | 1,114k |
kWh
|
7.0% |
- Natural Gas | $48k | - |
MMBtu
|
- |
Waste | $5.9k | |||
Productivity/Other | $41k | |||
TOTAL | $202k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
169
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,697k | 280k |
MMBtu
|
$7.75 |
- Electrical | $769k | 16,365k |
kWh
|
$0.061 |
- Natural Gas | $596k | 108k |
MMBtu
|
$6.52 |
580
Implemented Recommendations
3.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $45k | 3.5k |
MMBtu
|
1.2% |
- Electrical | $20k | 341k |
kWh
|
2.1% |
- Natural Gas | $15k | - |
MMBtu
|
- |
Waste | $2.2k | |||
Productivity/Other | $13k | |||
TOTAL | $60k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |