ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Breakfast cereal manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

14

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,637k 261k
MMBtu
$7.63
- Electrical $745k 14,418k
kWh
$0.060
- Natural Gas $590k 111k
MMBtu
$6.87

131

Recommendations

9.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $141k 17k
MMBtu
6.4%
- Electrical $84k 1,639k
kWh
11.4%
- Natural Gas $38k -
MMBtu
-
Waste $9.4k
Productivity/Other $8.7k
TOTAL $159k
*May be negative reflecting an increased cost component required to save energy and costs overall

12

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,727k 291k
MMBtu
$6.36
- Electrical $779k 15,977k
kWh
$0.050
- Natural Gas $629k 125k
MMBtu
$6.04

49

Implemented Recommendations

4.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $63k 5.3k
MMBtu
1.8%
- Electrical $29k 519k
kWh
3.2%
- Natural Gas $30k -
MMBtu
-
Waste $2.7k
Productivity/Other $1.0k
TOTAL $67k
*May be negative reflecting an increased cost component required to save energy and costs overall