ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Grain and oilseed milling
SIC 2+ Digits Required
3+ Characters Required for Products

80

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,474k 268k
MMBtu
$8.19
- Electrical $630k 13,809k
kWh
$0.066
- Natural Gas $593k 126k
MMBtu
$6.31

645

Recommendations

8.1

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $130k 14k
MMBtu
5.2%
- Electrical $65k 1,349k
kWh
9.8%
- Natural Gas $48k -
MMBtu
-
Waste $14k
Productivity/Other $47k
TOTAL $191k
*May be negative reflecting an increased cost component required to save energy and costs overall

75

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,509k 279k
MMBtu
$7.98
- Electrical $627k 14,185k
kWh
$0.064
- Natural Gas $622k 133k
MMBtu
$5.98

301

Implemented Recommendations

4.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $58k 5.2k
MMBtu
1.9%
- Electrical $24k 504k
kWh
3.6%
- Natural Gas $29k -
MMBtu
-
Waste $0.6k
Productivity/Other $44k
TOTAL $103k
*May be negative reflecting an increased cost component required to save energy and costs overall