ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Animal food manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

73

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $840k 124k
MMBtu
$7.99
- Electrical $334k 5,861k
kWh
$0.065
- Natural Gas $364k 63k
MMBtu
$5.84

559

Recommendations

7.7

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $99k 6.0k
MMBtu
4.8%
- Electrical $37k 585k
kWh
10.0%
- Natural Gas $34k -
MMBtu
-
Waste $1.3k
Productivity/Other $72k
TOTAL $172k
*May be negative reflecting an increased cost component required to save energy and costs overall

71

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $821k 121k
MMBtu
$8.01
- Electrical $331k 5,818k
kWh
$0.065
- Natural Gas $347k 61k
MMBtu
$5.84

259

Implemented Recommendations

3.6

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $33k 1.8k
MMBtu
1.5%
- Electrical $13k 172k
kWh
3.0%
- Natural Gas $7.4k -
MMBtu
-
Waste $0.1k
Productivity/Other $10k
TOTAL $43k