The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | Copper ore and nickel ore mining | |
| SIC | 2+ Digits Required | |
| 3+ Characters Required for Products | ||
3
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $10,522k | 1,847k |
MMBtu
|
$6.49 |
| - Electrical | $4,869k | 179,491k |
kWh
|
$0.039 |
| - Natural Gas | - | - |
MMBtu
|
- |
22
Recommendations
7.3
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $531k | 70k |
MMBtu
|
3.8% |
| - Electrical | $172k | 6,848k |
kWh
|
3.8% |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | - | |||
| TOTAL | $531k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
3
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $10,522k | 1,847k |
MMBtu
|
$6.49 |
| - Electrical | $4,869k | 179,491k |
kWh
|
$0.039 |
| - Natural Gas | - | - |
MMBtu
|
- |
8
Implemented Recommendations
2.7
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $240k | 40k |
MMBtu
|
2.1% |
| - Electrical | $96k | 3,858k |
kWh
|
2.1% |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | - | |||
| TOTAL | $240k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||