The ITAC Statistics page displays the average assessment results for the selected criteria.
6
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $22,799k | 3,851k |
MMBtu
|
$6.47 |
- Electrical | $13,408k | 290,774k |
kWh
|
$0.049 |
- Natural Gas | - | - |
MMBtu
|
- |
42
Recommendations
7.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $1,585k | 273k |
MMBtu
|
7.1% |
- Electrical | $1,337k | 26,634k |
kWh
|
9.2% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | $0.8k | |||
Productivity/Other | $252k | |||
TOTAL | $1,839k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
5
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $26,783k | 4,553k |
MMBtu
|
$6.07 |
- Electrical | $15,671k | 342,682k |
kWh
|
$0.045 |
- Natural Gas | - | - |
MMBtu
|
- |
17
Implemented Recommendations
3.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $231k | 35k |
MMBtu
|
0.8% |
- Electrical | $118k | 3,405k |
kWh
|
1.0% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $15k | |||
TOTAL | $247k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |