ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Mining (except oil and gas)
SIC 2+ Digits Required
3+ Characters Required for Products

42

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $4,982k 848k
MMBtu
$9.88
- Electrical $2,596k 58,296k
kWh
$0.059
- Natural Gas $556k 116k
MMBtu
$2.36

266

Recommendations

6.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $481k 60k
MMBtu
7.1%
- Electrical $275k 5,875k
kWh
10.1%
- Natural Gas $40k -
MMBtu
-
Waste $16k
Productivity/Other $236k
TOTAL $733k
*May be negative reflecting an increased cost component required to save energy and costs overall

40

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $5,168k 887k
MMBtu
$9.05
- Electrical $2,701k 60,879k
kWh
$0.058
- Natural Gas $583k 122k
MMBtu
$2.37

108

Implemented Recommendations

2.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $128k 8.2k
MMBtu
0.9%
- Electrical $35k 804k
kWh
1.3%
- Natural Gas $12k -
MMBtu
-
Waste $6.8k
Productivity/Other $61k
TOTAL $195k
*May be negative reflecting an increased cost component required to save energy and costs overall