ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Soil preparation, planting, and cultivating
SIC 2+ Digits Required
3+ Characters Required for Products

1

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $122k 7.1k
MMBtu
$17.20
- Electrical $57k 690k
kWh
$0.082
- Natural Gas -
-
MMBtu
-

4

Recommendations

4.0

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $29k 3.3k
MMBtu
47.3%
- Electrical $27k 326k
kWh
47.3%
- Natural Gas -
-
MMBtu
-
Waste -
Productivity/Other $0.1k
TOTAL $29k
*May be negative reflecting an increased cost component required to save energy and costs overall

1

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $122k 7.1k
MMBtu
$17.20
- Electrical $57k 690k
kWh
$0.082
- Natural Gas -
-
MMBtu
-

0

Implemented Recommendations

0.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy -
-
MMBtu
-
- Electrical -
-
kWh
-
- Natural Gas -
-
MMBtu
-
Waste -
Productivity/Other -
TOTAL -
*May be negative reflecting an increased cost component required to save energy and costs overall