ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Crop production
SIC 2+ Digits Required
3+ Characters Required for Products

12

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $550k 105k
MMBtu
$8.14
- Electrical $282k 9,321k
kWh
$0.062
- Natural Gas $60k 6.0k
MMBtu
$6.67

52

Recommendations

4.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $124k 5.4k
MMBtu
5.2%
- Electrical $49k 530k
kWh
5.7%
- Natural Gas $18k -
MMBtu
-
Waste $72k
Productivity/Other $6.8k
TOTAL $202k
*May be negative reflecting an increased cost component required to save energy and costs overall

10

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $567k 122k
MMBtu
$6.08
- Electrical $298k 10,900k
kWh
$0.049
- Natural Gas $47k 6.0k
MMBtu
$5.04

17

Implemented Recommendations

1.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $39k 0.9k
MMBtu
0.8%
- Electrical $3.5k 93k
kWh
0.8%
- Natural Gas $18k -
MMBtu
-
Waste $86k
Productivity/Other ($-1.5)k
TOTAL $124k
*May be negative reflecting an increased cost component required to save energy and costs overall