Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

715

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
KG0100 #04 Y:1997 Lease / purchase baler; sell cardboard to recycler $1,484 -
KG0100 #03 Y:1997 Lease / purchase baler; sell cardboard to recycler $4,554 -
KG0100 #02 Y:1997 Lower ceiling to reduce conditioned space $6,859 $1,744
KG0100 #01 Y:1997 Lower ceiling to reduce conditioned space $1,133 $248
KG0099 #08 Y:1997 Move product using mechanical means $50,960 $25,500
KG0099 #07 Y:1997 Separate and recycle scrap metal to foundry or for sale $1,440 -
KG0099 #06 Y:1997 Lease / purchase baler; sell cardboard to recycler $4,580 $7,950
KG0099 #05 Y:1997 Contract a wood pallet recycling company $5,200 -
KG0099 #04 Y:1997 Install timers and/or thermostats $808 $450
KG0099 #03 Y:1997 Reduce the pressure of compressed air to the minimum required $3,683 -
KG0099 #02 Y:1997 Turn off equipment when not in use $4,752 -
KG0099 #01 Y:1997 Use adjustable frequency drive or multiple speed motors on existing system $8,849 $16,900
KG0098 #06 Y:1997 Move product using mechanical means $5,117 $1,000
KG0098 #05 Y:1997 Lease / purchase baler; sell cardboard to recycler $2,153 $7,950
KG0098 #04 Y:1997 Lease / purchase baler; sell cardboard to recycler $3,655 -
KG0098 #03 Y:1997 Improved material handling (mixing and transfer) $4,212 $2,300
KG0098 #02 Y:1997 Use waste heat from hot flue gases to preheat $398 $1,600
KG0098 #01 Y:1997 Install timers and/or thermostats $667 $450
KG0097 #05 Y:1997 Re-arrange equipment layout to reduce labor costs $30,888 $43,000
KG0097 #04 Y:1997 Add equipment/ operators to reduce production bottleneck $596,163 $8,894