1,280
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
UL2411 #06 Y:2024 | 06 | 2024 | Use waste heat from hot flue gases to preheat | $35,308 | $50,000 |
n/a
|
UL2411 #05 Y:2024 | 05 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $5,372 | $5,000 |
n/a
|
UL2411 #04 Y:2024 | 04 | 2024 | Use insulation in furnaces to facilitate heating / cooling | $4,053 | $13,653 |
n/a
|
UL2411 #03 Y:2024 | 03 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,717 | $1,995 |
n/a
|
UL2411 #02 Y:2024 | 02 | 2024 | Lower temperature during the winter season and vice-versa | $746 | $2,700 |
n/a
|
UL2411 #01 Y:2024 | 01 | 2024 | Use solar heat to make electricty | $76,606 | $698,579 |
n/a
|
UA0288 #09 Y:2024 | 09 | 2024 | Utilize higher efficiency lamps and/or ballasts | $2,856 | $4,621 |
n/a
|
UA0288 #08 Y:2024 | 08 | 2024 | Install timers and/or thermostats | $1,656 | $994 |
n/a
|
UA0288 #07 Y:2024 | 07 | 2024 | Use solar heat to make electricty | $290,423 | $2,558,734 |
n/a
|
UA0288 #06 Y:2024 | 06 | 2024 | Optimize plant power factor | $8,607 | $5,049 |
n/a
|
UA0288 #05 Y:2024 | 05 | 2024 | Recover waste heat from equipment | $16,178 | $10,450 |
n/a
|
UA0288 #04 Y:2024 | 04 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $5,987 | $8,591 |
n/a
|
UA0288 #03 Y:2024 | 03 | 2024 | Replace hydraulic / pneumatic equipment with electric equipment | $2,549 | $1,031 |
n/a
|
UA0288 #02 Y:2024 | 02 | 2024 | Reduce the pressure of compressed air to the minimum required | $6,645 | $1,000 |
n/a
|
UA0288 #01 Y:2024 | 01 | 2024 | Utilize energy-efficient belts and other improved mechanisms | $9,634 | $1,046 |
n/a
|
SU0546 #04 Y:2023 | 04 | 2023 | Install / repair insulation on steam lines | $559 | $253 |
n/a
|
SU0546 #03 Y:2023 | 03 | 2023 | Utilize higher efficiency lamps and/or ballasts | $6,466 | $100 |
n/a
|
SU0546 #02 Y:2023 | 02 | 2023 | Eliminate or reduce compressed air usage | $626 | - |
n/a
|
SU0546 #01 Y:2023 | 01 | 2023 | Recharge batteries on during off-peak demand periods | $2,882 | - |
n/a
|
NT0012 #06 Y:2023 | 06 | 2023 | Reduce scrap production | $80,000 | $20,000 |