Assessment Year | 1986 |
---|---|
Principal Product | PERLITE & VERMICULITE |
NAICS |
n/a
|
SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
n/a
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $41,164 | 431,125 |
kWh
|
$0.095 |
Natural Gas | $140,038 | 19,872 |
MMBtu
|
$7.05 |
Fuel Oil #2 | $85,919 | 14,280 |
MMBtu
|
$6.02 |
Other Energy | $29,333 | 3,733 |
MMBtu
|
$7.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,443 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,686 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,819 | $3,000 |
$3,819
40,152
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $593 | $50 |
$593
6,155
kWh
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $154 | - |
$154
1,465
kWh
|
- | - | - | |
04 | 2.8223: Add air shields to trucks to increase fuel mileage | $2,256 | $3,000 | - | - | - |
$2,256
-
MMBtu
|
|
05 | 2.2511: Insulate bare equipment | $4,908 | $2,600 | - |
$4,908
-
MMBtu
|
- | - | |
06 | 2.2511: Insulate bare equipment | $2,327 | $600 | - | - |
$2,327
-
MMBtu
|
- | |
07 | 2.2511: Insulate bare equipment | $2,695 | $1,000 | - |
$2,695
-
MMBtu
|
- | - | |
08 | 2.2443: Re-use or recycle hot or cold process exhaust air | $251 | $700 | - | - |
$251
-
MMBtu
|
- | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $440 | $200 |
$440
4,689
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $17,443 | $11,150 |
$5,006
52,461
kWh
|
$7,603
-
MMBtu
|
$2,578
-
MMBtu
|
$2,256
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,686 | $7,550 |
$4,852
50,996
kWh
|
- |
$2,578
-
MMBtu
|
$2,256
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs