41
matching recommendations
$
$
| ARC | 2+ Digits Required | |
| NAICS | Rolled steel shape manufacturing | |
| SIC | 2+ Digits Required | |
| 3+ Characters Required for Products | ||
| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| LE0283 #24 Y:2008 | 24 | 2008 | Install occupancy sensors | $550 | $600 | |
| LE0283 #23 Y:2008 | 23 | 2008 | Utilize higher efficiency lamps and/or ballasts | $7,799 | $32,466 | |
| LE0283 #22 Y:2008 | 22 | 2008 | Reduce the pressure of compressed air to the minimum required | $312 | $240 | |
| LE0283 #21 Y:2008 | 21 | 2008 | Repair faulty insulation in furnaces, boilers, etc | $608 | $565 | |
| LE0283 #20 Y:2008 | 20 | 2008 | Minimize use of outside make-up air for ventilation except when used for economizer cycle | $718 | $300 | |
| LE0283 #19 Y:2008 | 19 | 2008 | Substitute hot process fluids for steam | $1,040 | $600 | |
| LE0283 #18 Y:2008 | 18 | 2008 | Install / repair insulation on steam lines | $1,121 | $1,000 | |
| LE0283 #17 Y:2008 | 17 | 2008 | Minimize use of outside make-up air for ventilation except when used for economizer cycle | $2,129 | $600 | |
| LE0283 #16 Y:2008 | 16 | 2008 | Install compressor air intakes in coolest locations | $5,319 | $800 | |
| LE0283 #15 Y:2008 | 15 | 2008 | Utilize energy-efficient belts and other improved mechanisms | $6,465 | $160 | |
| LE0283 #14 Y:2008 | 14 | 2008 | Reschedule plant operations or reduce load to avoid peaks | $7,947 | $7,000 | |
| LE0283 #13 Y:2008 | 13 | 2008 | Install vinyl strip / high speed / air curtain doors | $8,598 | $2,400 | |
| LE0283 #12 Y:2008 | 12 | 2008 | Cover open tanks | $9,339 | $10,000 | |
| LE0283 #11 Y:2008 | 11 | 2008 | Preheat combustion air with waste heat | $18,031 | $30,000 | |
| LE0283 #10 Y:2008 | 10 | 2008 | Replace boiler | $19,000 | $30,000 | |
| LE0283 #09 Y:2008 | 09 | 2008 | Use radiant heater for spot heating | $19,446 | $5,000 | |
| LE0283 #08 Y:2008 | 08 | 2008 | Preheat combustion air with waste heat | $21,508 | $30,000 | |
| LE0283 #07 Y:2008 | 07 | 2008 | Use adjustable frequency drive or multiple speed motors on existing system | $22,225 | $30,000 | |
| LE0283 #06 Y:2008 | 06 | 2008 | Repair or replace steam traps | $27,445 | $10,500 | |
| LE0283 #05 Y:2008 | 05 | 2008 | Reschedule plant operations or reduce load to avoid peaks | $28,610 | $12,000 |