ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
UU0148 #06 Y:2019 | 06 | 2019 | Utilize higher efficiency lamps and/or ballasts | $6,667 | $8,267 | |
UU0148 #05 Y:2019 | 05 | 2019 | Use computer programs to optimize hvac performance | $10,445 | $308 | |
UU0148 #04 Y:2019 | 04 | 2019 | Separate and recycle scrap metal to foundry or for sale | $21,723 | $100,000 | |
UU0148 #03 Y:2019 | 03 | 2019 | Size electric motors for peak operating efficiency | $205,559 | $25,240 | |
UU0148 #02 Y:2019 | 02 | 2019 | Reschedule plant operations or reduce load to avoid peaks | $292,277 | $82,400 | |
UU0148 #01 Y:2019 | 01 | 2019 | Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $4,526,086 | $11,242,113 |